245 | 00|aProject 4 - all-season road connecting Berens River and Poplar River First Nation |h[electronic resource] : |benvironmental assessment report. |
---|
246 | 17|aEnvironmental assessment report – Project 4 all-season road |
---|
260 | |aOttawa : |bCanadian Environmental Assessment Agency, |c2017. |
---|
300 | |axi, 170 p. : |bcol. maps |
---|
500 | |aIssued also in French under title: Projet 4 – route toutes saisons entre Berens River et la Première Nation de Poplar River : rapport d’évaluation environnementale. |
---|
500 | |aCover title. |
---|
500 | |a"June 2017.” |
---|
504 | |aIncludes bibliographical references. |
---|
520 | |a“Manitoba Infrastructure, the provincial department responsible for the agency formerly known as the East Side Road Authority, (the proponent) proposes to construct and operate a 94.1 km all-season, two lane, gravel public highway between the Berens River First Nation Reserve # 13 and the Poplar River First Nation Reserve #16, on the east side of Lake Winnipeg in Manitoba. The Project is one component of Manitoba’s East Side Large Area Transportation Network that will provide year-round transportation service for the remote and isolated communities on the east side of Lake Winnipeg. The Canadian Environmental Assessment Agency (the Agency) conducted an environmental assessment (EA) of the Project in accordance with the Canadian Environmental Assessment Act, 2012 (CEAA 2012). This EA Report summarizes the EA conducted by the Agency, including the information and analysis on the potential environmental effects of the Project considered by the Agency and the Agency’s conclusions on whether the Project is likely to cause significant adverse environmental effects, after taking into account the implementation of mitigation measures”--Executive summary, p. i. |
---|
692 | 07|2gccst|aRoad construction |
---|
692 | 07|2gccst|aEnvironmental impact assessment |
---|
710 | 1 |aCanada. |bCanadian Environmental Assessment Agency. |
---|
775 | 08|tProjet 4 – route toutes saisons entre Berens River et la Première Nation de Poplar River |w(CaOODSP)9.832326 |
---|
856 | 40|qPDF|s2.33 MB|uhttps://publications.gc.ca/collections/collection_2017/acee-ceaa/En106-157-2017-eng.pdf |
---|