1102 |aCanada Energy Regulator.|eauthor, |eissuing body.
24510|aCanada Energy Regulator reasons for decision in the matter of NOVA Gas Transmission Ltd. : |bapplication dated 23 May 2023 for approval of the North Montney mainline tolling methodology.
24614|aCanada Energy Regulator reasons for decision : |bNOVA Gas Transmission Ltd., RH-003-2023
2463 |aReason for decision : |bNOVA Gas Transmission Ltd. - RH-003-2023
264 1|aCalgary, Alberta : |bCanada Energy Regulator = Régie de l'énergie du Canada, |c2024.
264 4|c©2024
300 |a1 online resource (v, 35 pages) : |bcolour map.
336 |atext|btxt|2rdacontent
337 |acomputer|bc|2rdamedia
338 |aonline resource|bcr|2rdacarrier
4901 |a[Reasons for decision] ; |vRH-003-2023
500 |aIssued also in French under title: Régie de l'énergie du Canada, motifs de décision relativement à NOVA Gas Transmission Ltd. : demande datée du 23 mai 2023 visant à faire approuver la méthode de conception des droits de la canalisation principale North Montney.
500 |a"RH-003-2023."
500 |a"March 2024."
504 |aIncludes bibliographical references.
61020|aNOVA Gas Transmission Ltd.
650 0|aNatural gas pipelines|xRates|zBritish Columbia.
650 0|aNatural gas pipelines|zBritish Columbia|xCost of operation.
77508|tRégie de l'énergie du Canada, motifs de décision relativement à NOVA Gas Transmission Ltd. : |w(CaOODSP)9.940248
7760#|tNOVA Gas Transmission Ltd.|w(CaOODSP)9.932914
830#0|aReasons for decision (Canada Energy Regulator‏)|vRH-003-2023.|w(CaOODSP)9.906740
85640|qPDF|s790 KB|uhttps://publications.gc.ca/collections/collection_2024/rec-cer/NE22-1-2024-1-eng.pdf